The rendering of the internal walls is now done, and drying - you won't be able to see the brick lines once it's dry and painted. And has some magnificent art work, or a large TV, hanging in front of it.
More insulation has been slotted into the ceiling, and the heating panels have new wiring on them. With the roof now completed (except over the stairwell and garage), this will allow the plaster ceilings to go up, or under it all. I'd probably have started with the plaster and let gravity actually help me with the rest, but then again, I'm not qualified.
The posts for the roof deck are in place and waterproofed and the roof is complete. The deck will extend about a meter further to the left of the leftmost posts, and have a nice glass balustrade around it. At the back is the stairwell, waiting for some scaffolding to go around it so it can be enclosed and roofed, and also waiting for the spiral staircase to go into it. All the doors and windows for it are on site at least.
The skylight is now framed, and the north-facing louvred window is in. As a solar chimney it will let controlled amounts of light in, and vent hot air from the house in summer. Obviously it can do that right now, but it's a little too open to the elements for our liking.
The guttering and eaves are nearly finished, with some temporary drainage arrangements, and some temporary scaffolding arrangements.
We're even starting to see some of the joinery arriving with the first cupboards on site, ready to be installed.
And even our first shower is moving ahead rapidly!
Hmmm, maybe not.